Fire sprinkler work is usually design-build, so each bidder may be pricing a slightly different system. Exclusions are where they really part ways: underground fire service, backflow, the hydrant flow test, fire alarm wiring, firestopping and ceiling patching. Compare who designs it, what it connects to, and what it leaves out.

Level your fire sprinkler bids with this checklist →

Standard scope checklist

Send this to every bidder and ask them to mark each line Included, Excluded or give an Add $. Silence is not inclusion.

#Scope item
1Design: shop drawings and hydraulic calculations by the sprinkler contractor (or engineer)
2Hydrant flow test / water supply data
3Plan review and fire sprinkler permit fees
4Underground fire service to the building (or point of connection)
5Fire service tap and meter / detector check (utility requirements)
6Backflow preventer: furnished, installed and tested
7Riser, alarm valve, flow and tamper switches
8Fire department connection (FDC)
9System type per area: wet, dry, preaction
10Head type and finish: concealed, semi-recessed, upright
11Head locations centered in ceiling tile (if required)
12Standpipes (if required)
13Fire pump (if required) and its electrical service
14Seismic bracing where required
15Freeze protection: heat trace, dry systems, insulation
16Relocation of existing heads on TIs
17System drain-down and refill on existing systems
18Fire alarm monitoring wiring of flow / tamper switches
19Coring and firestopping of sprinkler penetrations
20Ceiling removal and replacement or patching
21Hydrostatic testing, flushing and acceptance test with the fire marshal
22Spare head cabinet and signage
23After-hours work / fire watch in occupied buildings
24Sales tax, bond and prevailing wage

Common exclusions and how they are worded

ExclusionTypical wordingWhy it mattersTypical cost to cover
Underground fire service
  • “Underground by others”
  • “Begins at flange 1 ft above finished floor”
Many sprinkler bids start at the riser inside the building. The underground line and tap belong to a site utility contractor, so make sure someone carries it.TBD
Backflow preventer
  • “Backflow by plumber”
  • “Excludes backflow testing”
The water utility usually requires a backflow assembly on the fire line. Decide who furnishes, installs and certifies it.TBD
Flow test & design
  • “Hydrant flow test by owner”
  • “Pricing based on assumed water pressure”
The system design depends on water supply data. If the real flow test comes in low, the design and price can change.TBD
Fire alarm wiring
  • “Electrical wiring of devices by others”
  • “Fire alarm by others”
Flow and tamper switches have to be wired to and monitored by the fire alarm system. That sits with the fire alarm or electrical contractor.TBD
Ceilings & patching
  • “Excludes ceiling removal / replacement”
  • “Excludes patching and painting”
On TIs, heads get moved through existing ceilings. Someone has to remove and replace tile or patch drywall.TBD
Firestopping & coring
  • “Firestopping by others”
  • “Excludes core drilling”
Sprinkler pipe through rated walls needs listed firestop. It's a frequent gap across all MEP trades.TBD
Fire pump
  • “Excludes fire pump”
  • “Pump electrical by others”
If the water supply can't meet demand, a fire pump may be needed, with its own room, power and testing. It's a major scope item.TBD
Freeze protection
  • “Excludes heat trace”
  • “Excludes freeze protection”
Pipe in unheated spaces, canopies or loading docks needs a dry system or protection. A wet-only bid may not work there.TBD
Head type & finish
  • “Standard heads”
  • “Semi-recessed in lieu of concealed”
Concealed heads cost more than standard ones. Check head type in finished areas against the spec.TBD
Fire watch & after-hours
  • “Excludes fire watch”
  • “Normal hours only”
When systems are shut down in an occupied building, a fire watch may be required. Ask who provides and pays for it.TBD

“Typical cost to cover” is TBD. We will publish ranges only once we have real, sourced data. Until then, use your own estimate or a confirmed add price from a bidder.

Questions to ask bidders

  1. Who prepares the shop drawings and hydraulic calculations, and are permit and plan review fees included?
  2. What water supply data did you design to? Is a hydrant flow test included?
  3. Where does your scope begin: at the street, at the building, or at the riser flange?
  4. Is the backflow preventer included? Furnished, installed and tested?
  5. Who wires the flow and tamper switches to the fire alarm?
  6. What head types did you price in finished areas?
  7. Are ceiling removal, replacement and patching included?
  8. Is firestopping of your penetrations included?
  9. Are drain-down, refill and any fire watch on the existing system included?
Placeholder

Bid-ready fire sprinkler contractors

Contractors who agree to price against the standard checklist above, with exclusions spelled out line by line. Listings are not live yet.

Featured listing

Your company · City, ST

Bids on the BidGaps checklist

Featured listing

Your company · City, ST

Bids on the BidGaps checklist

List your company →