Home / Trades / HVAC / Mechanical

HVAC / Mechanical: what bids leave out

HVAC bids can look comparable on tonnage and equipment brand and still cover very different work. One carries controls, test and balance, the crane pick, roof curbs and condensate piping. Another sets the units and runs the duct, and excludes everything that makes the system work as designed. Level on scope first.

Level your HVAC bids with this checklist →

Standard scope checklist

Send this to every bidder and ask them to mark each line Included, Excluded or give an Add $. Silence is not inclusion.

#Scope item
1Equipment per schedule: make, model, tonnage, efficiency (or approved equal)
2Equipment substitutions listed and called out
3Crane / rigging for rooftop units
4Roof curbs, curb adapters and structural support
5Roof penetrations, flashing and coordination with the roofer
6Ductwork: supply, return and exhaust per drawings
7Duct insulation and lining
8Grilles, registers and diffusers
9Exhaust fans (restroom, kitchen, specialty)
10Kitchen hood and grease duct (if any)
11Gas piping to equipment
12Condensate piping and drains
13Refrigerant piping for split systems
14Temperature controls: thermostats, BAS / DDC, programming
15Control wiring (low-voltage) vs. line voltage power by electrician
16Fire / smoke dampers and duct smoke detectors
17Test, adjust and balance (TAB) by an independent firm
18Startup, commissioning and owner training
19Demolition and disposal of existing equipment and duct
20Refrigerant recovery from existing equipment
21Temporary heating or cooling during construction
22Filters during construction and final filter change
23Coring, sleeves and firestopping
24Permits, mechanical inspections and fees
25Warranty term (parts vs. labor, compressor)
26Sales tax, bond and prevailing wage

Common exclusions and how they are worded

ExclusionTypical wordingWhy it mattersTypical cost to cover
Controls
  • “Controls by others”
  • “Standalone thermostats only”
  • “Excludes BAS integration”
A bid with basic thermostats isn't comparable to one carrying the specified building automation and programming. Controls are one of the biggest hidden scope differences.TBD
Test & balance
  • “Excludes test and balance”
  • “TAB by owner”
Without balancing, rooms run hot or cold and you can't prove the system meets design. It's often spec'd as owner-hired, so budget it either way.TBD
Crane & rigging
  • “Excludes crane”
  • “Crane by GC”
Rooftop units have to be lifted. Crane cost depends on unit weight and site access, and it's often excluded.TBD
Roof curbs & roofing work
  • “Curbs set by others”
  • “Excludes roofing / flashing”
  • “Excludes structural framing at openings”
New units need curbs, framed openings and flashing. These sit between the mechanical, roofing and structural trades, and gaps here cause leaks.TBD
Line-voltage electrical
  • “Power wiring by electrical contractor”
  • “Excludes disconnects”
The HVAC contractor typically wires controls and the electrician brings power and disconnects. Check that the two bids meet without a gap.TBD
Condensate & gas piping
  • “Excludes condensate piping”
  • “Gas piping by plumber”
Condensate drains and gas lines to equipment can be carried by HVAC or plumbing. Make sure one of them prices it.TBD
Fire / smoke dampers & duct detectors
  • “Duct detectors furnished by fire alarm contractor”
  • “Excludes fire dampers not shown”
Dampers and duct detectors are life-safety items that cross HVAC, fire alarm and electrical scopes. Spell out who furnishes, installs, wires and tests them.TBD
Equipment substitutions
  • “Pricing based on [brand] equipment”
  • “Or approved equal”
A lower bid may be based on different equipment than specified. Check model numbers, efficiency and warranty before you treat it as equal.TBD
Demolition & refrigerant recovery
  • “Excludes removal of existing equipment”
  • “Excludes refrigerant recovery”
Old units and duct have to come out, and refrigerant has to be recovered by a certified tech before disposal.TBD
Temporary conditioning
  • “Excludes temporary heat / cooling”
  • “Permanent equipment not to be used during construction”
Drywall, paint and flooring need climate control. If the permanent system can't be used, temporary units are a real cost.TBD

“Typical cost to cover” is TBD. We will publish ranges only once we have real, sourced data. Until then, use your own estimate or a confirmed add price from a bidder.

Questions to ask bidders

  1. What equipment did you price (make, model, efficiency)? Any substitutions from the schedule?
  2. Are controls included to the level in the spec, including programming and integration?
  3. Is test and balance included? By an independent firm?
  4. Are crane, rigging, curbs and curb adapters included?
  5. Who handles roof openings, framing and flashing at new units?
  6. Where does your wiring stop and the electrician's start? Who provides disconnects?
  7. Are condensate and gas piping included to every unit?
  8. Who furnishes, installs and wires fire/smoke dampers and duct detectors?
  9. What warranty is included, and does it cover labor?
Placeholder

Bid-ready HVAC contractors

Contractors who agree to price against the standard checklist above, with exclusions spelled out line by line. Listings are not live yet.

Featured listing

Your company · City, ST

Bids on the BidGaps checklist

Featured listing

Your company · City, ST

Bids on the BidGaps checklist

List your company →